The declaración de obra nueva (declaration of new building) is the deed by which you record that there is a house on your property. Until it is executed and registered, as far as the Land Registry (Registro de la Propiedad) is concerned you still own a bare plot: the house cannot be mortgaged or sold with legal certainty.
It is governed by article 28 of Royal Legislative Decree 7/2015. In the Madrid region the tax is 0.75 % and it is worked out on the cost of the works, not on the value of the house or the land.
Three routes, not one
Under construction
The works are declared as designed, not yet built. This requires the permit and a technician’s certificate of conformity with the design.
The usual route when there is a self-build mortgage: the bank wants the future building already tied to the property.
Completed
It also requires the certificate of completion (certificado final de obra), evidence of the requirements for delivery to users, the document authorising occupancy and the energy performance certificate.
If the building under construction was already registered, completion is recorded afterwards.
By age
The exceptional route of article 28.4, when legality can no longer be restored by lapse of time. No permit and no completion certificate.
In Madrid: six years as a general rule, fifteen on protected non-developable land.
What the notary and the land registrar require
The same things. Article 28.1 imposes them on notaries and article 28.2 on land registrars before they register. For a completed:
| Document | Rule |
|---|---|
| Building permit | Art. 152.b Law 9/2001 (Madrid) |
| Certificate of completion from a competent technician | Art. 28.1 TRLSRU; art. 12.3.e LOE |
| Declaration of compliance (declaración responsable) for first occupancy (in Madrid no longer a licence) | Art. 155.c Law 9/2001; art. 28.1.b TRLSRU |
| Libro del edificio (building manual), for filing at the Registry | Art. 202 LH |
| Ten-year insurance (seguro decenal) or the self-build exemption | Arts. 19.1.c and 20.1 LOE; second additional provision |
| Energy performance certificate for the completed building | Art. 28.1.b TRLSRU; RD 390/2021 |
| Georeferenced coordinates of the footprint occupied | Art. 202 LH |
The coordinates surprise a lot of people. Since the 2015 reform, the land occupied by the building has to be identified by its geographic reference coordinates. This is not a step the notary handles: it comes out of the technical work, and it is worth planning for.
The ten-year insurance and the ten-year trap
The second additional provision of the LOE exempts the individual self-builder (autopromotor) of a single detached house for their own use. So far, the good news. The small print says that if the house is transferred between living persons within ten years, the self-builder “unless otherwise agreed, shall be obliged to take out the cover for the remaining period”.
And the closing words are blunt: “public deeds of inter vivos transfer shall not be authorised or registered at the Land Registry without evidence and a record of the said cover having been constituted, unless the self-builder, who must show that they have used the dwelling, is expressly released by the acquirer”.
- The exemption holds while the house is for your own use
- The ten years run from the reception of the works
- Saying you have lived there is not enough: it has to be evidenced
- The release has to be express by the buyer
- It applies to a transfer in lieu of payment as well
- Inheritance is not covered: the rule speaks of transfers between the living
What it costs
The tax: stamp duty (actos jurídicos documentados)
| Item | In the Madrid region |
|---|---|
| Rate | 0.75 % |
| Taxable base | The real cost value of the new building declared. Not the market value. The land is not included |
| Filing deadline | 30 business days from execution of the deed, form 600 |
| Example | Declared cost of €300,000 → €2,250 |
Notary and Land Registry
The fee scales date from 1989 and are set in bands, with a general reduction of 5 %. For a declared value of €300,000, the basic scale comes to around €388 for the notary and €205 for the registry, before pages, copies, disbursements and VAT. The final invoice is appreciably higher and depends on how long the deed runs.
Why we do not give a closed range. We have checked the scales and the reduction, but not a total invoice range with a source we trust. We would rather say so than invent a figure that fails to add up later.
The order everything goes in
Certificate of completion
Signed by the architect and the building engineer (aparejador), with visado (professional association approval stamp).
Energy performance certificate
For the completed building, registered with the Madrid region.
Libro del edificio
Handed over by the architect directing the works and deposited at the town hall, which in Madrid is a condition for first occupancy.
Declaration of compliance for first occupancy
At the town hall. It is worth also asking for the certificate of conformity (acto de conformidad).
Deed of the completed new building
Before a notary, with all the documentation above.
Tax
Form 600, within 30 business days.
Registration
No legal deadline, but the entry of presentation lasts 60 business days.
Catastro and utilities
Form 900D and permanent supply contracts.
What happens if it is never declared
| Effect | Why |
|---|---|
| The house does not appear at the Registry: the property is still a plot | Art. 202 LH |
| The house cannot be mortgaged or sold with legal certainty | The bank requires the property registered with the building |
| A mismatch with the Catastro, possibly a file opened | Consolidated Cadastral Act |
| No registry protection against third parties or registered attachments | Arts. 32 and 34 LH |
| The tax does not become time-barred: it falls due on the deed, not on building | Art. 31.2 of the consolidated act on the tax |
And do not confuse the lapse of planning enforcement with legalisation: the time limits running out prevents demolition, but the building is left non-conforming (fuera de ordenación), with a marginal note at the Registry.
Frequently asked questions
Do I need ten-year insurance if I build my own house?
No, not if you are the individual self-builder of a single detached house for your own use: the second additional provision of the LOE exempts you. But if you sell within ten years you must take it out for the time remaining, unless the buyer expressly releases you and you can show you have used the house.
What value do I pay the tax on?
On the real cost of carrying out the works as declared, not on the market value and without including the land. Article 70.1 of the tax regulations says so. In the Madrid region the stamp duty (actos jurídicos documentados) rate is 0.75 %.
Can I execute the deed without first occupancy?
In Madrid, yes, by producing the declaration of compliance and showing that the period has passed without an obstructive decision, under article 28.1.b of the Land Act. Even so, it is worth also obtaining the town hall’s certificate of conformity, because registry practice is demanding.
Is the libro del edificio compulsory in order to register?
Yes. Since November 2015, article 202 of the Mortgage Act (Ley Hipotecaria) has required it to be produced for filing at the Registry, and the Directorate General has ruled that this applies to detached houses and to self-build too.
I built years ago without a permit. Can I register it?
You may be able to, by the route in article 28.4 of the Land Act, if planning legality can no longer be restored. In the Madrid region the period is six years as a general rule and fifteen on protected non-developable land. You have to evidence the date of completion and that there is no planning enforcement note.
One deed or two?
It depends on the financing. With a self-build mortgage, the bank usually requires the building under construction to be registered before it releases funds, and completion is recorded afterwards. With no mortgage, the deed of the completed new building is executed directly.
We prepare all the technical documentation for the deed
Certificate of completion, energy performance certificate, libro del edificio and georeferenced coordinates. Coordinated with first occupancy, which is what usually holds up the signing at the notary’s.