A self-build mortgage is not paid out in one go. It is released in tranches, against progress certificates (certificaciones de obra), and those certificates are signed by your architect and carry the professional association approval stamp (visado). The last tranche, usually around 15 %, is held back until the certificate of completion (certificado final de obra).
This page is written from that side: the side of whoever signs the documents that make the bank pay. It is the part no bank product sheet explains, and the part that decides whether the works have cash or not.
How it differs from an ordinary mortgage
| Ordinary mortgage | Self-build mortgage | |
|---|---|---|
| Subject | A house that already exists | A plot and works not yet built |
| How the money arrives | In full on signing | In instalments, against certificates |
| Security | The existing house | The plot plus the future building, valued as if finished |
| Who certifies progress | Nobody: there is no progress | The architect directing the works |
| Grace period (carencia) | Not common | Common while the works run, up to two years |
How the money is actually released
Bank contracts are fairly explicit once you read them. One of those we have looked at provides that up to 85 % of the principal is drawn down “in line with the progress of the investment and the rate of execution”, evidenced by “certificates issued by the Architect Director of the works”, and it holds back the remaining 15 % until the certificate of completion “duly stamped by the Official Professional Associations”.
Another is even clearer about the formal requirement: evidence of the degree of execution “shall be provided by means of certificates issued by the architect directing the works, with the visado of the respective professional association”.
| Tranche | Indicative weight | What releases it | Who signs |
|---|---|---|---|
| Initial | 40–50 % | Deed, land registry extract and new building under construction registered | Notary and Land Registry |
| Interim | 35–45 % | Progress certificate with visado at each milestone: foundations, structure, envelope, finishes | The architect directing the works |
| Final | 10–20 % | Certificate of completion with visado, and sometimes first occupancy and registration | Architect and building engineer |
Where the cash flow breaks. The bank pays against work already carried out. The builder usually asks for advance payments or invoices at thirty days. You have to cover that gap yourself, and it is the number one practical problem of a financed self-build. It is worth agreeing it with the builder before signing, not after.
Why a design with visado changes the valuation
Valuations are governed by Order ECO/805/2003, updated in 2025. Its article 4 defines the value on the assumption of a finished building as the value a building that is on the drawing board or under construction will foreseeably reach on the date it is finished, if it is built within the estimated timescale and with the characteristics of its design.
The consequence is direct, and few people spell it out:
Only the plot has value
Without a design with visado and a permit, the valuer can only value the land. The figure is much lower, and so is the loan that comes from it.
The finished house has value
With a design with visado and a permit, the valuer issues a value on the assumption of a finished building, which is the base the bank calculates from. The design is not a formality: it is what multiplies the valuation.
If planning documentation is missing, or the property cannot be inspected, the valuation comes out with conditions or warnings, and with a condition attached the bank does not usually move. The updated rules also require the valuer to have the design with visado, the permit or authorisation, and the certificate of work carried out.
What technical documentation you will be asked for
- Design with the professional association’s visado
- Building permit or administrative authorisation
- The builder’s construction budget
- Valuation on the assumption of a finished building
- Progress certificates with visado at each tranche
- Certificate of completion with visado
- Deed of new building under construction, registered
- All-risks construction insurance
The ten-year insurance: what the law says and what the bank does
The law exempts you. The second additional provision of the LOE leaves out the individual self-builder of a single detached house for their own use, with the well-known exception of a sale within ten years.
The bank is another matter. It cares about being able to resell the property if it has to enforce the mortgage, and there is evidence that many lenders ask for the insurance anyway. That said: we have not found a single official bank website that requires it in writing. It is decided case by case, so ask before you sign rather than assume it is off the table.
How much they lend
| Lender | What it states | Source |
|---|---|---|
| Santander | Up to 100 % of the priced works, capped at 70 % of the replacement value of the finished construction. It does not finance the land. Grace period up to two years | Its website, consulted in August 2026 |
| BBVA | Drawdown in instalments against a certificate with visado. Its contract publishes no percentage or maximum term | Its official loan contract |
| Another lender consulted | 85 % available in phases and 15 % held back until the certificate of completion | Its official contract |
Why we do not publish a table with every bank. Tables circulate with percentages and rates for a dozen lenders, taken from comparison sites. We have not been able to confirm them on each bank’s own website, and publishing as a lender’s condition something that lender does not say strikes us as wrong. These three we have verified from a primary source.
The eight real problems
Cash flow gap
The bank releases against work carried out; the builder asks for money on account. You fill that hole.
Final retention blocked
Some contracts tie the last tranche to registration at the Land Registry, not just to completion. Worth reading before you sign.
Drawdowns cut back
If the valuation falls, or you skip items that were priced, the lender can trim the tranches to come.
Budget overrun
Cost above the tender that was valued is not financed.
Design changes
They mean amending the permit, and can force a revaluation.
Late certification
Every certificate that slips is a month of interest with the works not moving.
Maximum period for the works
Contracts set one, and going past it entitles the bank to suspend drawdowns.
Works left unfinished
With no completion certificate there is no last tranche and no registration of the completed building, and the loan already drawn is repaid anyway.
What the studio can do. Almost all of these problems are managed through site supervision: certifying on time and with the visado in order, anticipating design changes instead of discovering them, and scheduling the certificates with the bank and the builder before starting. A certification schedule agreed by all three parties avoids most of the scares.
The ten steps of a self-build, with the mortgage in its place, are in the self-builder’s guide (PDF, in Spanish) (in Spanish).
Frequently asked questions
Does the bank hand over all the money when I sign?
No. It is structured in tranches: an initial drawdown, interim drawdowns against progress certificates and a final tranche held back until the certificate of completion. In one contract we have looked at, that final retention is 15 %.
Who signs the certificates that release the money?
The architect directing the works, and the bank contracts say so expressly: “certificates issued by the architect directing the works, with the visado of the respective professional association”. Without that signature and that visado, the bank does not release the tranche.
Do they finance the land?
It depends on the lender. Santander states on its website that it does not: it requires proof that you own the plot. Others include it according to comparison sites, but we have not been able to confirm it on each bank’s website, so we do not take it as given.
How much do they lend?
The ceiling is usually the lower of a percentage of the valuation on the assumption of a finished building and a percentage of the works budget. Santander publishes that it finances up to 100 % of the construction budget, capped at 70 % of the replacement value of the finished construction.
Do I need the ten-year insurance?
The LOE exempts the individual self-builder of a single detached house for their own use. Whether the bank asks for it anyway is another matter, because it cares about being able to resell the property. We have found no official bank website that requires it in writing: it is decided case by case.
What is the grace period (carencia)?
An initial period in which you repay no capital and pay only interest, and only on what you have actually drawn down. Santander states up to two years. It coincides with the building period, when you are also paying rent where you live.
Can I apply for one without a permit?
Not with certainty. Without a design with visado and a permit, or at least an administrative authorisation covering a good part of the budget, the valuation comes out with a condition and the bank cannot value on the finished-building assumption. That is where a design with visado multiplies the valuation.
What if the budget runs away, or the works stop?
Cost above the tender that was valued is not financed: you put that in. And works that have stopped stop generating certificates, so they stop receiving money. With no completion certificate the last tranche is not released and the completed building is not registered.
The certificates that release your bank’s money are the ones we sign
As site supervisors (dirección facultativa) we issue the interim certificates with visado and the certificate of completion, which are the documents the bank pays against. And we set up the certification schedule with the builder before starting, so the works do not stop waiting for money.