Health and safety study: when the basic one is enough and when it is not

When you need a full health and safety study and when a basic one will do, who drafts it, and why a detached house almost always needs a coordinator.

Fran CortésFran Cortés, architect
14 August 2026 · updated 5 October 2026 · 7 min read

Every set of works with a design needs a health and safety study, and without one there is no visado and no permit. The question is not whether you need one, but whether the basic study is enough or you need the full study.

On a detached house the basic study is usually enough. But watch the threshold of 500 person-days, which trips much earlier than the budget one. And a health and safety coordinator is needed almost always, even if you hire the trades directly yourself.

€450,759.08
Budget threshold for the full study
500 person-days
The threshold that trips first on a detached house
Almost always
Need for a coordinator during the execution phase

When the full study and when the basic one

Article 4.1 of Royal Decree 1627/1997 requires a full study if any one of these four cases applies:

CaseThresholdOn a detached house
Contract price for the works (presupuesto de ejecución por contrata)≥ €450,759.08
The BOE (Spain’s official gazette) still says 75 million pesetas
Possible on large works. VAT included
Duration and number of workersMore than 30 working days and more than 20 workers at the same timeBoth requirements are cumulative: they rarely both apply
Volume of labourMore than 500 person-daysThe one that trips first. Six operatives × a hundred days already exceed it
Type of worksTunnels, galleries, underground conduits and damsNot relevant

On designs that fall into none of them, the basic study is enough (article 4.2).

The threshold most often overlooked. Almost everybody looks at the budget one and assumes a basic study will do. The 500 person-day one is what decides most medium-sized detached houses, and it is worth estimating well when the design is drafted, not discovering it on site.

What each one contains

Full study

Five documents (art. 5.2)

Descriptive report: procedures, equipment, avoidable and unavoidable risks, measures and protective equipment, assessing how effective they are.

Particular conditions of contract with the rules that apply. Drawings. Quantities for every item. And a budget of its own, which the contractor cannot cut.

Basic study

One document (art. 6.2)

It specifies the safety rules that apply, identifies avoidable risks with their technical measures, lists unavoidable ones with their protective equipment, takes account of the other activities on site and details the measures for work of particular risk.

No conditions of contract, no drawings, no quantities and no budget of its own.

Both must include forecasts and information useful for later work on maintenance and upkeep, the part most often forgotten and the one the owner will end up needing.

A study is not the same as a plan

Health and safety studyHealth and safety plan
PhaseDesignExecution
Who produces itA competent technician appointed by the developer (promotor)Each contractor, one each
What it isThe forecast of the risks in the designHow that contractor will carry out the works, with its own plant and system
Who approves itIt forms part of the designThe coordinator for the execution phase, before work starts; if there is no coordinator, the site supervision team (dirección facultativa)

The plan may propose alternative measures, but with technical justification and without lowering the levels of protection or, in the case of the full study, the total amount. And any later change needs express approval.

The coordinator: almost always needed

This is the part that surprises a self-builder most. There are two possible coordinators, and the rules differ:

PhaseWhen it is compulsoryOn a detached house
Design (art. 3.1)Where more than one designer is involved in preparing the designNormally not, if a single architect signs
Execution (art. 3.2)Where more than one undertaking is involved, or one undertaking and self-employed workers, or several self-employedPractically always. A builder plus a subcontractor is enough

And appointing one does not relieve you of anything. Article 3.4 is literal: “the appointment of the coordinators shall not relieve the developer of their responsibilities”. In a self-build, the developer is you.

If you hire the trades directly yourself

This is the most frequent question, and the rules give a clear answer. Article 2.3 says that when the developer hires self-employed workers directly, they shall be deemed to be the contractor, but it adds an express exception: this “shall not apply where the activity contracted relates exclusively to the construction or repair that a head of household may contract in respect of their own home”.

How you hireWhat you areWhat falls to you
A building companyDeveloper onlyThe study, appointing the coordinator, approving the plan through the coordinator
Several self-employed workers directly, for your own homeDeveloper. The head-of-household exception keeps you from being the contractorBasic study and coordinator in execution compulsory
Several companies directlyDeveloper; each company is a contractorCoordinator compulsory; each company with its own plan
With your own plant and your own employeesContractor (Law 32/2006, art. 3)Safety plan, opening of the workplace, preventive resources, training, protective equipment and health surveillance

The head-of-household exception saves you from being the contractor, not from being the developer. And if you put labourers of your own on site, you become an employer for all purposes.

The obligations that get forgotten

  • The prior notice (aviso previo) was repealed in 2010: today it is the notification of opening of the workplace
  • It is filed by the contractor, before work begins, with the plan attached
  • The site incident book (libro de incidencias) is issued by the professional association of the technician who approved the plan
  • It must be kept on site at all times, held by the coordinator
  • A repeated entry means a copy must be sent to the Labour Inspectorate (Inspección de Trabajo) within 24 hours
  • Without the study there is no visado and no permit (art. 17.1)

Penalties

Failures by the developer are classified in article 12.24 of the consolidated act on social order offences and penalties as a seriousoffence: not appointing coordinators when required, failing in the duty to have the study drawn up, or the study having “significant and serious defects or shortcomings”.

DegreeMinorSeriousVery serious
Lower€45–485€2,451–9,830€49,181–196,745
Middle€486–975€9,831–24,585€196,746–491,865
Upper€976–2,450€24,586–49,180€491,866–983,736

To which are added the surcharge on social security benefits, the stopping of the works and civil and criminal liability.

Where more than one company works on site, a coordinator is also needed during execution. We explain it in health and safety coordinator.

Frequently asked questions

Does my house need a full study or a basic one?

Basic, unless one of the four cases in article 4.1 of Royal Decree 1627/1997 applies. Be careful with the volume of labour: five operatives working a hundred days exceed 500 person-days, and that trips well before the budget threshold of €450,759.08.

Do I need a health and safety coordinator on a detached house?

In practically every case, yes. Article 3.2 requires one where more than one undertaking is involved, or one undertaking and self-employed workers, or several self-employed. The only works that escape are those carried out by a single undertaking with no subcontractors and no self-employed, which is very rare.

If I hire the trades directly myself, do I become the contractor?

For your own home, no: article 2.3 has an express exception for “the construction or repair that a head of household may contract in respect of their own home”. But you are still the developer, so the basic study and the coordinator remain compulsory. And if you hire workers of your own, you become a contractor for all purposes under article 3 of Law 32/2006.

Does the prior notice (aviso previo) still exist?

No. It was repealed by Royal Decree 337/2010. What is filed today is the notification of opening of the workplace, with the safety plan attached, and the contractor files it before work begins.

Who approves the builder’s safety plan?

The health and safety coordinator for the execution phase, before the works start. If no coordinator has to be appointed, the site supervision team approves it.

Can my architect draft it?

Yes, as a competent technician appointed by the developer. And without the study there is no visado of the design and no municipal permit: article 17.1 says so.

We draft it with the design, not afterwards

The health and safety study comes out of the design itself, with a real estimate of person-days, which is what decides whether the basic one is enough. And we tell you from the start whether you will need a coordinator, so it does not come as a surprise on the day of the setting-out record (acta de replanteo).

Sources. Royal Decree 1627/1997, articles 2, 3, 4, 5, 6, 7, 13, 17 and 19, with article 18 repealed by Royal Decree 337/2010. Order TIN/1071/2010. Law 32/2006 on subcontracting in the construction sector, article 3. Royal Legislative Decree 5/2000, articles 12.23, 12.24, 13.8 and 40.2, as worded by Law 10/2021. Technical Guide for construction works of the Instituto Nacional de Seguridad y Salud en el Trabajo.