Every set of works with a design needs a health and safety study, and without one there is no visado and no permit. The question is not whether you need one, but whether the basic study is enough or you need the full study.
On a detached house the basic study is usually enough. But watch the threshold of 500 person-days, which trips much earlier than the budget one. And a health and safety coordinator is needed almost always, even if you hire the trades directly yourself.
When the full study and when the basic one
Article 4.1 of Royal Decree 1627/1997 requires a full study if any one of these four cases applies:
| Case | Threshold | On a detached house |
|---|---|---|
| Contract price for the works (presupuesto de ejecución por contrata) | ≥ €450,759.08 The BOE (Spain’s official gazette) still says 75 million pesetas | Possible on large works. VAT included |
| Duration and number of workers | More than 30 working days and more than 20 workers at the same time | Both requirements are cumulative: they rarely both apply |
| Volume of labour | More than 500 person-days | The one that trips first. Six operatives × a hundred days already exceed it |
| Type of works | Tunnels, galleries, underground conduits and dams | Not relevant |
On designs that fall into none of them, the basic study is enough (article 4.2).
The threshold most often overlooked. Almost everybody looks at the budget one and assumes a basic study will do. The 500 person-day one is what decides most medium-sized detached houses, and it is worth estimating well when the design is drafted, not discovering it on site.
What each one contains
Five documents (art. 5.2)
Descriptive report: procedures, equipment, avoidable and unavoidable risks, measures and protective equipment, assessing how effective they are.
Particular conditions of contract with the rules that apply. Drawings. Quantities for every item. And a budget of its own, which the contractor cannot cut.
One document (art. 6.2)
It specifies the safety rules that apply, identifies avoidable risks with their technical measures, lists unavoidable ones with their protective equipment, takes account of the other activities on site and details the measures for work of particular risk.
No conditions of contract, no drawings, no quantities and no budget of its own.
Both must include forecasts and information useful for later work on maintenance and upkeep, the part most often forgotten and the one the owner will end up needing.
A study is not the same as a plan
| Health and safety study | Health and safety plan | |
|---|---|---|
| Phase | Design | Execution |
| Who produces it | A competent technician appointed by the developer (promotor) | Each contractor, one each |
| What it is | The forecast of the risks in the design | How that contractor will carry out the works, with its own plant and system |
| Who approves it | It forms part of the design | The coordinator for the execution phase, before work starts; if there is no coordinator, the site supervision team (dirección facultativa) |
The plan may propose alternative measures, but with technical justification and without lowering the levels of protection or, in the case of the full study, the total amount. And any later change needs express approval.
The coordinator: almost always needed
This is the part that surprises a self-builder most. There are two possible coordinators, and the rules differ:
| Phase | When it is compulsory | On a detached house |
|---|---|---|
| Design (art. 3.1) | Where more than one designer is involved in preparing the design | Normally not, if a single architect signs |
| Execution (art. 3.2) | Where more than one undertaking is involved, or one undertaking and self-employed workers, or several self-employed | Practically always. A builder plus a subcontractor is enough |
And appointing one does not relieve you of anything. Article 3.4 is literal: “the appointment of the coordinators shall not relieve the developer of their responsibilities”. In a self-build, the developer is you.
If you hire the trades directly yourself
This is the most frequent question, and the rules give a clear answer. Article 2.3 says that when the developer hires self-employed workers directly, they shall be deemed to be the contractor, but it adds an express exception: this “shall not apply where the activity contracted relates exclusively to the construction or repair that a head of household may contract in respect of their own home”.
| How you hire | What you are | What falls to you |
|---|---|---|
| A building company | Developer only | The study, appointing the coordinator, approving the plan through the coordinator |
| Several self-employed workers directly, for your own home | Developer. The head-of-household exception keeps you from being the contractor | Basic study and coordinator in execution compulsory |
| Several companies directly | Developer; each company is a contractor | Coordinator compulsory; each company with its own plan |
| With your own plant and your own employees | Contractor (Law 32/2006, art. 3) | Safety plan, opening of the workplace, preventive resources, training, protective equipment and health surveillance |
The head-of-household exception saves you from being the contractor, not from being the developer. And if you put labourers of your own on site, you become an employer for all purposes.
The obligations that get forgotten
- The prior notice (aviso previo) was repealed in 2010: today it is the notification of opening of the workplace
- It is filed by the contractor, before work begins, with the plan attached
- The site incident book (libro de incidencias) is issued by the professional association of the technician who approved the plan
- It must be kept on site at all times, held by the coordinator
- A repeated entry means a copy must be sent to the Labour Inspectorate (Inspección de Trabajo) within 24 hours
- Without the study there is no visado and no permit (art. 17.1)
Penalties
Failures by the developer are classified in article 12.24 of the consolidated act on social order offences and penalties as a seriousoffence: not appointing coordinators when required, failing in the duty to have the study drawn up, or the study having “significant and serious defects or shortcomings”.
| Degree | Minor | Serious | Very serious |
|---|---|---|---|
| Lower | €45–485 | €2,451–9,830 | €49,181–196,745 |
| Middle | €486–975 | €9,831–24,585 | €196,746–491,865 |
| Upper | €976–2,450 | €24,586–49,180 | €491,866–983,736 |
To which are added the surcharge on social security benefits, the stopping of the works and civil and criminal liability.
Where more than one company works on site, a coordinator is also needed during execution. We explain it in health and safety coordinator.
Frequently asked questions
Does my house need a full study or a basic one?
Basic, unless one of the four cases in article 4.1 of Royal Decree 1627/1997 applies. Be careful with the volume of labour: five operatives working a hundred days exceed 500 person-days, and that trips well before the budget threshold of €450,759.08.
Do I need a health and safety coordinator on a detached house?
In practically every case, yes. Article 3.2 requires one where more than one undertaking is involved, or one undertaking and self-employed workers, or several self-employed. The only works that escape are those carried out by a single undertaking with no subcontractors and no self-employed, which is very rare.
If I hire the trades directly myself, do I become the contractor?
For your own home, no: article 2.3 has an express exception for “the construction or repair that a head of household may contract in respect of their own home”. But you are still the developer, so the basic study and the coordinator remain compulsory. And if you hire workers of your own, you become a contractor for all purposes under article 3 of Law 32/2006.
Does the prior notice (aviso previo) still exist?
No. It was repealed by Royal Decree 337/2010. What is filed today is the notification of opening of the workplace, with the safety plan attached, and the contractor files it before work begins.
Who approves the builder’s safety plan?
The health and safety coordinator for the execution phase, before the works start. If no coordinator has to be appointed, the site supervision team approves it.
Can my architect draft it?
Yes, as a competent technician appointed by the developer. And without the study there is no visado of the design and no municipal permit: article 17.1 says so.
We draft it with the design, not afterwards
The health and safety study comes out of the design itself, with a real estimate of person-days, which is what decides whether the basic one is enough. And we tell you from the start whether you will need a coordinator, so it does not come as a surprise on the day of the setting-out record (acta de replanteo).