It is the first question almost every client asks us, and the one that is usually answered worst. The typical answer is a price per square metre of construction, and that is it. But that figure is only half the answer. The real cost of building a house includes VAT, the professional team, what the town hall charges, servicing the plot, a contingency reserve and, if you do not have one yet, the plot itself.
We explain each item using the figures we work with at the studio. And if you want the figure for your own case, with your municipality and your square metres, use our construction cost calculator.
How much does it cost to build a house?

- The works for a medium-high quality architect-designed home cost between €1,500–1,800/m² built. These are contract prices: they already include the builder’s overheads and profit.
- Adding everything else (VAT, professional team, town hall, plot servicing and contingencies), the real cost ends up 35 % to 50 % above the price of the works.
- And that is before the land. The plot, with its taxes and costs, is separate.
A real example to give you a sense of scale: a 300 m² home in Las Rozas comes to around €540,000 of construction, which ends up well above €800,000 with a pool and kitchen.
The items that make up the real cost
1. The works (contract price)
This is what the builder charges: foundations, structure, façades, roof, services, windows and doors, and finishes. It depends on the floor area, the quality of materials and the ground.
Not every square metre costs the same. As a guide, compared with the €/m² of the living space:
- Basement for a garage, storage or plant room: around 60 %. If it is habitable (with windows, a lightwell and fully fitted out), practically the same as the house.
- Covered porch: around 45 %.
- Open terrace: between 15 % and 20 %.
The fully fitted kitchen (units, worktop and appliances: about €15,000 in medium quality, €25,000 in high and €40,000 in luxury) and the pool (a standard one, about €25,000) are usually separate.
2. VAT on the works
If you build as an autopromotor (self-builder) and contract the works directly with the builder, the construction of a dwelling is taxed at 10 %, whether or not it is your main home. Professional fees and any materials you buy yourself are taxed at 21 %. That is why it pays to include the materials in the building contract.
3. The professional team: design and site supervision
To build a home, the law requires four professional services: the proyecto básico (basic design), the proyecto de ejecución (construction drawings) and the dirección de obra (site supervision, by the architect), plus the dirección de ejecución (works supervision, by the building engineer, arquitecto técnico or aparejador), as well as health and safety coordination. At our studio, the four mandatory phases including health and safety coordination start from €24,000. We do not quote prices per phase: we study each case and give you a fixed price.
We explain it in detail in architect’s fees for a detached house.
On top of this come preliminary studies worth doing before the design: the topographic survey (about €500–600) and the geotechnical survey (from €700 to €1,600 plus VAT, depending on the size of the house and whether it has a basement).
4. What the town hall charges

This is the item that surprises people most, because it varies a lot even between neighbouring municipalities. There are two charges:
- The ICIO (construction tax): the law sets a maximum of 4 % and each town hall chooses its own rate.
- The permit fee, which some town halls charge on top of the ICIO and others do not.
In the Madrid region, the two together add up to between 3 % and 7 % of the construction budget, depending on the municipality. Many town halls also ask for bonds (for waste and for site works) that are returned at the end. You will find the rates for each municipality, checked one by one, in our guide to the ICIO and the building permit.
5. Servicing the plot
- External: water, electricity and drainage connections up to the plot. From €0 to around €20,000, depending on how ready it is.
- Internal: access, walls, earthworks and garden. On a steeply sloping plot it can exceed €100,000.
6. Insurance, notary and Land Registry
The ten-year structural insurance (seguro decenal, compulsory if you sell the house within ten years, and always highly advisable), the new-build deed and its registration, and the stamp duty (actos jurídicos documentados) on that deed. We explain it in the guide to the new-build declaration.
7. Contingency reserve
We recommend setting aside 10 % of the cost of the works. A good, complete and fully measured set of construction drawings is what reduces unexpected costs the most.
8. The plot, if you do not have one
On top of the purchase price come its taxes: if you buy from a private individual, the ITP (transfer tax; 6 % in the Madrid region); if you buy from a company, 21 % VAT plus stamp duty. Plus notary and Land Registry costs.
Before buying, check what you can build on it: what can I build on my plot? and how buildable area is calculated (in Spanish). If it is rural land, first read whether you can build on rural land (in Spanish).
Free PDF guide (in Spanish)
Get the full worked example as a PDF
“Cuánto cuesta construir tu casa” (How much it costs to build your house): a 150 m² home on a plot on the outskirts of Madrid, item by item and with taxes included. The guide is in Spanish. We will email it to you.
- The nine items: land, surveys, permit, professional team, works, plot servicing, extras, insurance and contingencies.
- The total as a range, from €1,500–1,800/m² of works.
- What almost nobody adds up until it is too late.
What most quotes leave out
- Interest on the self-build mortgage during the works: the loan is drawn down against stage certificates, and that interest is real money. We explain it in the guide to the self-build mortgage.
- The licencia de primera ocupación (first occupancy licence), which also varies a lot from one municipality to another. See the first occupancy guide.
- A difficult plot: slope, rock, a high water table or retaining walls. The geotechnical survey shows this, which is why it is done before the design.
Does a detached house cost more than a terraced one?

For the same floor area and quality, the detached house usually costs more: it has more external façade to build and insulate, needs fencing around the whole perimeter and bears the full cost of servicing its plot. The permit and paperwork are the same. We explain the differences in detached, semi-detached and terraced houses.
How we keep costs under control at the studio
Fran Cortés is an architect (COAM no. 21.503) and a building engineer (arquitecto técnico, COAATM no. 105.287), and signs off projects with a team of architects and building engineers. More than 300 homes carry the studio’s signature. This is how we work on the budget:
- Before we draw, we fit the house to your total budget, not just the budget for the works.
- First proposal in drawings and realistic images within 10–15 days, with weekly changes until the house is finalised (5–6 versions on average).
- Basic design in 6–8 weeks to apply for the permit, and construction drawings while it is being processed: when the permit arrives, you can already ask several builders for comparable quotes.
- We help you choose a builder and supervise the works independently of them, to keep control of quality, timescales and stage certificates.
The works usually take between 10 and 12 months. We work throughout Spain, mostly in the Madrid region and on the Costa del Sol (Málaga).
Calculate the cost of your house or book your free 30-minute consultation with the architect.
And for how long each phase takes, month by month, see how long it takes to build a house.
Frequently asked questions
How much does it cost per square metre to build a house?
For a medium-high quality architect-designed home, the works cost between €1,500–1,800/m². That is the price of the works: the total cost, with VAT, professional team, taxes and plot servicing, ends up 35 % to 50 % higher, before the land.
Which items are most often forgotten when working out the cost of a house?
VAT on the works, the town hall’s taxes and fees (between 3 % and 7 % in the Madrid region), servicing the plot, the contingency reserve and mortgage interest during the works.
How much does an architect charge to design a house?
At our studio, the four mandatory phases (basic design, construction drawings, site supervision and works supervision), including health and safety coordination, start from €24,000. Each case is studied and given a fixed price. See fees.
What VAT applies to building a house?
The construction of a dwelling that you contract directly with the builder: 10 %, whether or not it is your main home. Professional fees and any materials you buy yourself: 21 %.
How long does it take to build a house?
The basic design for the permit takes 6–8 weeks; the permit depends on the town hall; and the works take between 10 and 12 months.
Is it cheaper to build or to buy a house?
It depends on the area, the land and the house you want. We compare both in building a house from scratch or buying one ready-made (in Spanish).